(2208) Group scheduling

By clicking on the Group ID Scheduling the following dialog appears. 

Here you can schedule an offloading or reloading process for all DataProviders with the same Group ID and maximum degree of parallelism:

  • Max. parallel DataProviders – maximum number of DataProviders running in parallel.
  • Max. parallel subrequests – maximum number of subrequests running in parallel per DataProvider.


Maximum number of running jobs is defined by the following formula:

  • (Max. DPs * Max. subreq.) + Max. DPs + 1